Arthur Ravenel Jr. Bridge
Vertical Access, working with Freyssinet
LLC and the South Carolina
Department of Transportation, recently completed an investigation of
the cables of the longest cable-stayed bridge in North America.
The Arthur Ravenel Jr. Bridge (more popularly known as the Cooper
River Bridge) is located between Charleston and Mount Pleasant over the
Cooper River in South Carolina. Completed
in 2005, the bridge was designed and built by Parsons
Brinckerhoff and Palmetto Bridge Constructors to replace two
obsolete bridges: the Grace Memorial Bridge and the Pearman Bridge.
While the Grace Memorial Bridge had narrow lanes and a low
vehicle weight limit, both bridges lacked the necessary clearance for
large container ships to safely pass underneath.
Prior to the demolition of these outdated bridges, even though
Charleston is one of the busiest container seaports in the United
States, many large container ships could only pass under the bridges
during low tide. The Arthur Ravenel Jr. Bridge is named after the South
Carolina senator who is largely credited with finding the $700 million
of funding required for construction.
When Palmetto Bridge Constructors was contracted to work on the
bridge, it signed a design-build contract, which allowed construction to
begin sooner than with a conventional project schedule.
The bridge deck is supported by 128
wire cables, which hang in a harp-like arrangement from two diamond-shaped
towers. The towers reach 575 feet above the water and are connected
by the 1,546-foot long main span. With
a clearance of almost 200 feet over the Cooper River, the Arthur Ravenel
Jr. Bridge is designed to allow large container ships to easily reach
upstream port terminals. The
base of each tower is shielded from container ship collisions by a large
rock island. Designed to
stop a runaway ship before it hits a tower, the islands surround the
tower bases with one acre of protective stone at water lever.
On the bed of the Cooper River, the base of each island covers
five acres. The islands are
made of Newfoundland limestone, with some of the individual stones
weighing up to two tons.
Each of the stay cables is housed in
a high-density polyethylene (HDPE) duct, comprised of many sections
butt-welded together. Each
duct section is composed of two layers of co-extruded HDPE, so that
there is an inner black layer and an outer white layer.
Along the entire length of the ducts are double helical ribs
designed to shed water and increase aerodynamic stability.
At the roadway level anchorages, all of the stay cables are
fitted with internal dampers, which are sealed to prevent water
infiltration. In addition
to these internal dampers, the longest 16 cables in the main span are
fitted with fixed external dampers.
Although the bridge does not currently have cross tie cables, the
longest 24 cables in the main span are equipped with steel collars to
allow the future addition of cross ties, if necessary.
Vertical Access was appointed by
Freyssinet to document conditions on a representative sample of the
bridge’s stay cables as the first phase of a warranty inspection
schedule. Each tower
supports 64 cables and is equipped with two elevators, one on each side
of the roadway. Kent, Donn, Mike, and Keith were able to access the tops of
the towers to begin the cable inspections using the construction elevators.
Their first day on site yielded slow progress and a lot of
learning, which was to be expected given this was VA’s first exposure
to a cable stay bridge. The
following days brought faster progress and a lot of jumaring.
Midweek thunderstorms forced the team to take a much-needed
break, and allowed them to explore downtown Charlestown.
By the end of the week the Vertical Access team had jumared close
to 2 vertical miles, eaten authentic southern grits, and was ready to
head back to Ithaca for some office time.